Help, the ladies' washroom is sinking!

In recent weeks the Working Party has been busy rescuing the back of the clubhouse. Old age and a long term water leak from the ladies' changing room facilities had rotted the main beam supporting the back wall of the clubhouse. It needed to be replaced, so, rather like repairing a flat tyre on your car, the back of the building was jacked up and a new beam fitted. Thanks to Ray Hall for pictures of this interesting operation.

And thanks to all the Working Party for carrying it out. They work all winter on these sorts of jobs and could be forgiven if they felt undervalued by members, as they d a huge amount of vital maintenance work. So thank you all!

Clubhouse1.png
The damaged area before work started
P1040426.png
First beam removed
P1040431.png
Preparing to remove the next beam
P1040427R.png
Supporting the building with a jack
P1040432.png
Putting the jack in place
P1040433.png
Needs to be absolutely right!
P1040434.png
The jack takes the strain
P1040435.png
Damaged beam
P1040438.png
Removing the beam
P1040439.png
Preparing the brick supports
P1040442.png
Cleaning them up.
P1040444.png
Last beam coming out
P1040445.png
Nearly there!
P1040447.png
Brick support ready for cleaning up
P1040448.png
The new beam
P1040453.png
Rebuilding the brick supports
P1040455.png
Preparing the damp proof course
P1040456.png
It's got to be level!
P1040457.png
Finishing the brick supports
P1040459.png
Ready to lift into place
P1040461.png
Ready to slide in
P1040462.png
Nearly there
P1040463.png
New beam in place
P1040464.png
The jacks come out
FinishedBeam.jpg
The finished beam in place